|
Main
Plant
Process
Building
Once
used to reprocess spent (used) nuclear fuel, the Main Plant
Process Building at the West Valley Site is
a five-story, heavily-shielded reinforced concrete
structure. Some areas of the Main Plant contain residual
radioactive contamination from past reprocessing activities.
Removing equipment and debris and preparing the facility for
demolition is a major focus of the present work scope.
Through June 2011, WVES will:
-
Deactivate and decontaminate
ten cells
(chambers) and several ancillary areas
-
Process and package radioactive debris and ship offsite
for disposal
-
Prepare the structure for demolition
Radioactive Waste Management
Since
1999, the WVDP has shipped approximately 1.25 million cubic feet of low-level
radioactive waste for offsite disposal. WVES is safely
processing and disposing of the remaining legacy (stored)
low-level radioactive waste and newly-generated waste. Key
waste management activities include:
-
Process and shipment of stored legacy low-level
radioactive waste and highly-contaminated equipment and
debris,
-
Package and disposal of newly-generated waste resulting
from decontamination and dismantlement work, and
-
Continued onsite safe storage of waste with no current
pathway for disposal, including 275 canisters of
solidified high-level radioactive waste.
Infrastructure
Reduction
As the
WVDP moves toward site closure, large-scale infrastructure
reduction activities at the site have significantly reduced
the number of structures on the site. From now through 2011,
WVES expects to remove about 60 additional structures,
further preparing the site for future long-term management
and eventual closure. Major facilities to be removed during
this period include:
-
Storage facilities, including areas used for the storage
of waste and materials associated with operation of the
facility,
-
Wastewater treatment facilities, and
-
Waste transfer piping that connects the Main Plant to
the Waste Tank Farm.
North Plateau Groundwater Plume
The
WVDP is preparing to install a permeable treatment wall
(PTW)near
the leading edge of a contaminated groundwater plume at the
WVDP site to capture Strontium-90 in the groundwater. This
action is being taken to mitigate expansion of the plume.
The wall is under design, with actual construction scheduled
for 2010.
Testing of cation exchange capacities of
zeolites for use in the PTW is being directed by University
at Buffalo (UB) staff. Column studies are in progress at UB
and in the site's environmental laboratory.
Waste Tank and Vault Drying System
Removal of residual liquids and drying the underground tanks
and vaults were identified as best-management practice for
near-term management of the underground Waste Tank Farm. The
tanks were formerly used to store liquid radioactive waste.
In June 2009, WVES awarded a contract for the design and
construction of a tank and vault drying system.
High-level Waste Canister Storage System
The
WVDP is reviewing storage facility options that would allow
the relocation of the 275 canisters of high-level waste from
the WVDP’s Main Plant. Movement of the canisters to
alternate onsite storage is required to allow demolition of
the Main Plant building.
|